Leeson Road information.
Update July 22 2025
An extensive array of monitoring equipment now in place at Leeson Road continues to provide regular reliable data about the ground conditions.
The equipment was installed as a major part of the project to re-open the road, which connects Shanklin and Ventnor, following a huge landslip there in December 2023.
Some of the equipment is located within three boreholes, the deepest of which is well over 100 ft to the bottom. The equipment in the boreholes and on the surface of Leeson Road measure ground movement and water pressure to inform Island Roads and the IW Council of changes that may indicate land movement.
In addition to weekly reviews of this data, there are weekly site inspections.
Examination of all the latest data indicates the highway is stable with no significant changes or immediate risks identified. The risk rating for Leeson Road remains green.
Monitoring Insights:
The ongoing accumulation of data throughout different seasons and conditions will continue to advance our knowledge and understanding of The Landslip and guide future management strategies.
For archived updates on Leeson Road and Ventnor accessibility visit this link here.