Essential utility works will be taking place along Horsebridge Hill, Parkhurst and Elenors Grove, Fishbourne, as part of planned infrastructure schemes delivered by Southern Water.
These works will take place during the dates shown below.
Horsebridge Hill
Works start: Monday 26 January 2026
Works end: Late April 2026
Elenors Grove
Works start: Monday 2 February 2026
Works end: Late April 2026
Island Roads has made efforts to rearrange its own highways maintenance works around these schemes, where possible.
These are Southern Water schemes. Southern Water is responsible for delivering the works and for communicating directly with stakeholders, including local residents and businesses affected by the activity.
Island Roads granted the works space on the network on behalf of the Isle of Wight Council (the Highways Authority) and assisted Southern Water in the planning of diversion routes.
Find out about Island Roads’ role in managing utility works on the highway here.
Horsebridge Hill scheme information
Elenors Grove scheme information
The diversion routes can also be found on www.one.network
Contacts
Southern Water
For queries about the works taking place directly in and around the Southern Water works sites themselves, this includes questions about:
Please contact Southern Water:
Email: Jenny Keirle, Customer Laision, Clancy, jenny.keirle@clancygroup.co.uk
9am to 5pm, Monday to Friday
Phone: Call Southern Water 0330 3030 368. When calling quote PRN 835149 for Horsebridge Hill and PRN 835149 for Elenors Grove)
Online: www.southernwater.co.uk/contact-us
Island Roads
For issues relating to the diversion routes, including matters such as:
Please contact Island Roads via:
Email: info@islandroads.com
Reports will be managed through Island Roads’ normal processes.