Two Ryde roads set for improvement work

 Two busy Ryde roads are to be improved during October.

Sections of Green Street are to be reconstructed and resurfaced in work starting on October 6 and expected to last seven working days.

Then, similar work is scheduled to take place in Queen’s Road from October 20 and also last seven working days.

Because the work seeks to address the underlying issues that have caused the surface to deteriorate quicker than expected, deeper-than-usual excavations are required meaning the roads must remain closed at all times during the projects.

If possible, the roads may be opened over the weekend as long as it is safe to do so. Pedestrian access will be maintained.

The work has been programmed for outside of the main summer season and also to make use of the school half-term break for the Queens Road site.

An Island Roads spokesman said: “It is sadly not possible to undertake work of this nature in busy roads without causing some disruption. However, addressing the issues that have caused deterioration of the road surface will hopefully reduce the need for future maintenance.

“We would like to thank residents and road users for their understanding and co-operation in advance.”

Please note that for various reasons, including ground conditions and inclement weather, the works are subject change.

Information boards will be placed at both locations prior to work beginning and updates will be given on Island Roads’ X (formerly Twitter) account. Residents will also receive letters giving more information about the work.

 

Latest News

Latest on X

Please find attached an Immediate Closure for Worsley Road, Gurnard. The closure is necessary to enable Island Roads to maintain network safety repairs. @iow_council

Island Roads have closed Lushington Hill, Newport. This closure is necessary to enable Island Roads to maintain network safety.
For more information, please visit https://one.network
@iow_council

Immediate Closure for Drake Road, Newport from its junction with St Johns Road for a distance of 26 metres in a Northerly direction.

The closure is necessary to enable Southern Water to carryout urgent repairs. @iow_council