Progress continues at Godshill

The major highway improvement scheme through Godshill moves to the third and final phase on Monday.

This phase is the longest in the project – tackling the section between Church Hollow and a point east of the main car park.

So far, work is on schedule. The project is programmed to continue until December 12, when work will pause for Christmas and New Year. Work will resume on January 4. The road will be fully re-opened during this pause.

Due to the likelihood of some extreme weather at this time of the year, the scheme has been permitted to last until January 29 but all attempts will be made to finish as soon as possible.

So far Island Roads, who provide the Island’s highway services in partnership with the Isle of Wight Council, has been able to re-open the road between Friday evening and Monday morning and it remains the intention to do so for the remainder of the scheme.

During the project, Island Roads has also co-ordinated other highway works – such as street-lighting maintenance – to take place during the closure. Island Roads has also co-ordinated with Southern Water so that Southern Water can use the closure to repair its apparatus.

An Island Roads spokesperson said: “We know this work, while needed, has had an impact on the local community and we are really grateful for the understanding and support local residents and businesses have shown.

“We have worked hard to keep the community informed along the way and, wherever possible, we have used the closure and reduced traffic to carry out or co-ordinate other necessary work which we hope will prevent future disruption.

“Once again, we would also like to reinforce the message that businesses are open during the work. Please continue to support them.”

Latest on X