UPDATE May 10.

The current carriageway improvement works in Church Litten, Newport are progressing well.

We have moved on to Phase 2 (the northern end of Church Litten) today.

This means there will be no through access between Litten Park entrance and South Street. The diversion route will be via Medina Avenue, St Georges Approach, St Georges Way, Coppins Bridge, East Street and South Street. Access top the superstores and petrol station remains. (insert map)

As originally planned, Church Litten will from Friday evening to Monday morning, be open over the weekend via the right-hand lane. (insert map)

On Monday we will revert to the Phase 2 arrangements as per the above.

You can view the Phase 2 traffic plan here

To view the weekend traffic management plans, please click here

We would like to thank you in advance for your ongoing assistance in enabling us to complete these works. Your understanding and co-operation is very much appreciated.